Cable Manufacturer Case Study: A Data-Centre Campus

Cable Manufacturer Case Study: A Data-Centre Campus

An MEP contractor needed 12/20 kV feeders and a fire circuit into two data halls with low smoke sheath and tight risers. One order covered both duties.

Case Details

Cable Manufacturer Case Study: A Data-Centre Campus

An MEP contractor had two data halls to energise in twenty weeks, and on the last job it bought its medium voltage feeders and its fire circuit from two suppliers. The feeders went in without trouble. The fire circuit arrived late, in the wrong sheath, and had to be re-pulled through a busy riser. We took both duties on one order, with a low smoke sheath and a documented bend radius.

Project Snapshot

Item

Detail

Client

Mechanical and electrical contractor

Site

Two data hall buildings on a single campus

Project

Medium voltage feeders and a fire performance circuit

Products

12/20 kV XLPE insulated cable, armoured cable, fire performance circuit

Material and finish

Copper conductor, XLPE insulation, copper screen, low smoke halogen free sheath

Load range

3 x 150 mm² feeders, 12/20 kV system, minimum bend radius 15 x diameter

Factory lead time

18 working days from approved drawing to dispatch

On-site time

14 days of staged delivery to match the pulling programme

Outcome

Both duties delivered on one order, risers pulled without a re-pull

The Problem: A Busy Riser and Two Suppliers

The risers were the first constraint. Cable trays were sized early, when the feeder routes were still schematic, and the as-built routes had two extra bends. A cable specified to a minimum bend radius the riser does not allow cannot be pulled, and forcing one damages the screen and insulation in a way that does not show until the cable is energised.

The second constraint was fire performance. A circuit that keeps working while the building is evacuated has to survive the fire itself and must not add smoke or halogen to a space full of people and equipment. That rules out an ordinary PVC sheathed cable, which is what the contractor had budgeted for last time.

The third problem was coordination. Two suppliers means two lead times, two delivery sequences and one contractor carrying the risk of the later one.

Why We Chose LSZH Armoured XLPE Over Three Other Constructions

Unarmoured XLPE with a PVC sheath. Excluded. Cheaper, and unacceptable in an occupied hall: PVC releases dense smoke and acid gas in a fire, the opposite of what a data hall evacuation needs.

Mineral insulated cable for the fire circuit. Excluded. Superb fire performance and expensive, slow to install and stiff, the wrong profile for a riser with tight bends and a twenty week programme.

A separate supplier for each duty. Excluded. It splits the lead time risk onto the contractor and splits the sheath and screen documentation over two factories.

LSZH sheathed, armoured XLPE for the feeders, with the fire circuit from the same plant. Selected. One order, one specification route and one delivery sequence, with mechanical protection where the cable is pulled rather than ducted.

The Cable We Manufactured

The feeder is a 12/20 kV XLPE insulated cable with a copper conductor, a copper tape screen for fault current and earthing continuity, and a low smoke halogen free outer sheath. Mechanical protection is armoured construction where the route is exposed in a riser or shared trench, as the as-built route required. The 12-20kV XLPE insulated power cable is the feeder supplied here.

The fire circuit is built to the three hour condition at 950 °C, so it keeps working through an evacuation rather than failing at the start. It is a flexible construction because it has to be pulled by hand around the riser bends.

Bending radius was resolved with the contractor before production, not in a note on the drawing. We supplied the minimum radius and the pulling tension limit with the approval drawing, so the site team knew what the cable would accept. Our armoured electrical cable range covers the same duty where ducting is not available.

Installation: How the Work Ran

Production ran 18 working days from the approved drawing. Delivery was split into three calls over 14 days so the contractor could pull the first feeder while the second hall was still being built, keeping 640 m of cable out of a compound with no room for it.

Each drum arrived with the test certificates, the drum length and the pulling limit printed on the reel and in the paperwork. The riser pull was done with a tension meter on the winch line, watched by the contractor's supervisor against the limit we supplied. The fire circuit was delivered on the same schedule as the feeder that shared its route, so both cables went into the riser in one pull session.

Testing and Quality Control

Cable is inspected by batch rather than by sample: conductor resistance, insulation thickness, screen continuity and sheath dimensions are measured, and each batch is routine tested before release. The plant's own laboratory carries out the type and routine tests rather than sending work out.

The contractor asked for a partial discharge and a voltage withstand record per drum length, supplied with the dispatch documents, and the fire circuit came with its test record from the same plant. On site, an insulation resistance check was carried out after each pull and before termination, the check that catches a pull-related fault while it is still fixable.

Results: What the Numbers Show

Both halls were energised on the original date. The risers took the feeder and the fire circuit in one pull session, and no cable had to be re-pulled or re-ordered, the failure that cost the contractor six weeks on its previous project.

Termination went smoothly because the screen and sheath dimensions matched the drawing, and the fire circuit passed its continuity test first time. Buying both duties from one plant also removed the coordination risk from the contractor's own programme, the part hardest to price at tender. The contractor now uses our guide to choosing armoured cable when it writes its own cable clauses.

What This Case Means for Your Project

Cable is ordered on schedule and blamed on site. The two failure points are the ones nobody quantifies at tender: the bend radius in the as-built route, and the lead time of whichever supplier finishes last.

If you are powering a data hall, a substation or an industrial building, send us the route, the fault level, the sheath requirement and the energisation date. We will propose the construction, state the bend radius and pulling limits in writing, provide the batch test records, and quote to your programme. Send your cable schedule to our team and we will come back with a delivery plan per drum.